Al-Ghabawi Sanitary Landfill is Jordan's largest engineered municipal solid waste facility, located east of Amman and operated by the Greater Amman Municipality (GAM). Jordan Biogas Company took over the full operation and maintenance of the landfill gas power plant and wellfield infrastructure in 2021.
JBC manages the complete lifecycle of gas extraction, treatment, and power generation at the site — from the wellfield network through to the engine hall and grid interconnection — delivering 4.68 MW of continuous clean electricity directly to GAM.
The scope of JBC's work at Al-Ghabawi extends beyond the power plant itself: our team is fully responsible for the operation and maintenance of 4 capped landfill cells containing a total of 740 gas extraction wells (Cell 1: 148, Cell 2: 132, Cell 3: 197, Cell 4: 263). The landfill is designed for 9 cells in total, with cells 5 and 6 currently under construction.